Work Section 1 Work Section 2 Work Section 3 Work Section 4 Work Section 5 Work Section 6 Work Section 7 Work Section 8 Work Section 9 Work Section 10 Work Section 11 Work Section 12 Work Section 13 Work Section 14 Work Section 15 Work Section 16 Work Section 17 Work Section 18

 

 

Detailed Appraisal of Proposal

Note to see the details of the pictures and the drawings, click on the images below.

       

     Thurso River4.jpg (113338 bytes)                    Thurso River5.jpg (152024 bytes)

                    Footbridge                                    Footbridge and path to Mall
            Mall from East Bank

The detailed sections of work described thereafter are identified and numbered on the General Arrangement drawing No RC01.

Click on the links below or to the left to see the details of the 18 work sections that comprise this project:

  1. Wheelchair access from Mall to footbridge

  2. Repairs to Riverbank

  3. Updating the Play Area

  4. Updating West bank footpath

  5. Renewal of Woodlands

  6. Upgrade West bank gravel path

  7. Repair gabion baskets

  8. Wheelchair access/Cemetery bridge

  9. Raise sections of path, East bank

  10. Bridge, Lade Path and Platform

  11. Reclaim existing track

  12. Raise path at Lade crossover

  13. Bulb planting

  14. Drainage to wet areas

  15. Removal of dead trees, Boating Pond, etc

  16. New path between footbridge and Salmon Pool

  17. Viewing platform at Salmon Pool

  18. Benches, bins, etc

 