Programme of Works

Much thought has been given to the question of Programming and while it will be appreciated that the selection of certain Work Sections will be dictated by the appropriate availability of funding the following tentative conclusions are presented for consideration.

It is felt that in order to maintain enthusiasm and purposefulness the overall programme should be laid out to cover the shortest period of time possible while still retaining a semblance of reality.  Accordingly a programme period of 5 years has emerged as realistic.  The outline of the programme is detailed below and is based on the Work Sections previously identified.  It should be noted that a number of activities extend over the 5 year period and in the case of Section 5, which is the renewal of the tree belt, an overall period of between 5 and 10 years is possible.  

Year Section Work
1 2 Repairs to Riverbank
1 4  Upgrade West bank Footpath
1 5 Renewal of Woodlands (partial)  
1 6 Upgrade West Bank Gravel Path  
1 16 New Path at Salmon Pool (partial)  
2 1 Wheelchair Access Mall (footbridge)  
2 5 Renewal of Woodlands (partial)  
2 7 Repair Gabion Baskets  
2 16 New Path at Salmon Pool (partial)  
3 5 Renewal of Woodlands (partial)  
3 8 Wheelchair Access Cemetery Bridge  
3 9 Raise Sections of East Bank Path  
3 13 Bulb Planting  
3 14 Drainage to Wet Areas  
3 16 New Path at Salmon Pool (partial)  
4 3 Upgrading Play Area (partial)  
4 5 Renewal of Woodlands (partial)  
4 10 Lade Path, Bridge and Platform  
4 11 Reclaim Existing Track  
4 12 Path at Lade Crossover 
4 15 Boating Pond, etc (partial)  
4 18 Benches, Bins, etc (partial)  
5 3 Upgrading Play Areas  
5 5 Renewal of Woodlands  
5 15 Boating Pond, etc  
5 17 Viewing Platform at Salmon Pool  
5 18 Benches, Bins, etc  

      